SG Inc. completed another 2.8MW community solar project in Reisterstown, MD. This is the fourth Maryland community solar project this year and third overall in Baltimore County since inception of the program.
SG Inc. knocked out a 500kW ground mount system in 3 weeks in Henrico, Virginia. This apartment complex will soon be powered by a super clean solar installation!
SG Inc. knocked out a 500kW flat roof installation in just 2.5 weeks at the Sunbelle food processing plant in Jessup, Maryland. This installation reflects what SG Inc. strives for on every job: perfect planning and perfect execution!
SG Inc. broke ground on a 3rd Maryland Community solar project in Hagerstown, MD. This site had a lot of bedrock. It was engineered with Terrasmart racking and each foundation was pre-drilled and screwed …
SG Inc. broke ground on a Maryland Community solar project in Bowie, MD. Anyone that has worked in Prince George County Maryland knows the permitting challenges here. With SG Inc.’s experience, this installation went just as fast as any other – even with 2 months of grading the site!
SG Inc. broke ground on a Maryland Community solar project in Hancock, MD. This awesome installation of bifacial modules has a 35kV interconnection that is right next to I-70 – making for a really nice drone shot!
SG Inc. broke ground on a 16MW tracker in Danville, Virginia. This former golf course will soon be home to a brand new Italian tracker system (Valmont), an above ground CAB system and TMEIC inverter banks.
As part of customer appreciation, SGI selected valued customer Accomac county Virginia to give back an 8kW system free of charge. This system was installed on their Public Safety Building will save Accomac County nearly $1,000/year …
SG Inc. completed (3) turnkey sloped roof installations totaling 1.4MW at Hanover, Virginia at Oak Knoll Middle School, Hanover High School and Cool Springs Elementary school. Each school will all be producing clean power from super clean electrical installations!
SG Inc. completed a crane pick of Quest Renewable solar trusses on top of Shady Grove parking garage in Rockville, MD. The crane pick required a 9,000 lb lift at a 245’ radius which required a 500 ton crane. The crane was setup between 3AM and 7:30AM and was hook ready by 8:00AM. By 3PM, all (14) trusses were installed.