UMD Shady Grove gets new carport

SG Inc. completed a crane pick of Quest Renewable solar trusses on top of Shady Grove parking garage in Rockville, MD. The crane pick required a 9,000 lb lift at a 245’ radius which required a 500 ton crane. The crane was setup between 3AM and 7:30AM and was hook ready by 8:00AM. By 3PM, all (14) trusses were installed.
SG Inc completed 3MW in Ellenville NY

SG Inc. completes one of two 3MW fields in Ellenville, NY for Cypress Creek Renewables. The 4 week project consisted of Terrasmart racking, 1500V system, 2MW SMA inverter, (14) combiner boxes and 13.2 kV interconnection with (7) new utility and customer poles.
SG Inc completes Schenectady ground mount for Tesla

SG Inc. completes a 1.5 MW field in Schenectady NY for Tesla. This system consisted of fixed tilt DCE Racking and (31) Huawei inverters.