Baltimore Ground Mounts

SGI completed (2) projects totaling 3.8MW DC for Exyte Energy in the Spring of 2019 which included medium voltage overhead lines and medium voltage switchgear. SGI worked closely with the permitting and inspections department at Baltimore county to ensure all regulations and expectations were met from start to finish. The result was a smooth closeout of all […]
Canandaigua Solar Field

In Fall of 2018, SGI completed a 3MW ground mount for Cypress Creek Renewables. This project was completed in 6 weeks from the start of construction. The scope included low voltage and high voltage work with new utility poles and a 13.2kV interconnection. Other main components included SMA’s 2.5 MW inverter, SolarBos harnesses and combiner boxes and Locus […]
Anne Arundel Schools

SG Inc. used off-site prefabrication to complete one of two 1.4 MW complex ground mounts in a 4 week timeline. The challenges included strict electrical technical specifications and oversight, while installing another projects at the same time in Carroll County, MD. To accomplish this, we did extensive project pre-planning and utilized off-site pre-fabrication.
Wor Wic Community College

About: SG Inc. completed a 2.6MW installation for Tesla at the start of 2019. SG Inc. completed the project in turnkey fashion including the civil, post driving, racking/module installation, low voltage electrical and high voltage electrical including new utility poles with a 25kV interconnection.
Albany NY Solar Field 1

In winter of 2018, SGI completed a 3MW ground mount for Cypress Creek Renewables. The challenges included weather conditions, night/weekend work, a long duct bank of 3” and 5” conduits and 40’ concrete slab built on unlevel terrain that required import of more than 120 tons of stone. The project was completed on time and received permission […]
Hancock Solar Field (Pittman)

In Winter of 2020, SGI completed a turnkey 2.8MW ground mount for Nautilus Solar. This project consisted of CPS 125kW inverters, Adani bifacial modules and a 35kV interconnection.
Hagerstown Solar Field (Hostetter)

In Spring of 2020, SGI completed a turnkey 2.8MW ground mount for Nautilus Solar. This project was completed in 6 weeks from the start of construction. The scope included low voltage, high voltage and fiberoptic work with new 1,000’ utility pole run and a 13.2kV interconnection.
Bowie Solar Field (QAB)

In winter 2020, SGI completed a turnkey 2.8MW ground mount for Nautilus Solar. This project included over 25,000 yards of grading, CPS 125kW inverters, new low voltage and high voltage switchgear, an 800’ long 6” duct bank long run and fire access roads and barriers.
Ringgold/Danville Solar Field

In early 2020, SGI was awarded a 16MW ground mount tracker in Ringgold, VA. This project is slated to be complete August 2020.
Henrico Solar Field

SG Inc. completed turnkey electrical installation on a 500kW fixed tilt ground mount in June of 2020.